Harper College will be closed Tuesday, November 5 in observance of Election Day.
Bldgs. L,P,R power shutdown - 11/17/2024 - 11/20/24
ComEd and contractors will be onsite Sunday, November 17 through Wednesday, November 20 for a power shutdown for Buildings L, P and R.
Schedule:
Bldg. B to M Steam Piping, 5/24/2024 - 10/18/2024
Contractors will be repairing the steam piping from Bldg. B to Bldg. M. This will affect multiple areas - Bldg. S, the elevated track in Bldg. M will be closed and the east side of the gym will be closed and only open for select events.
Bldg. B, B117c TR ADA Remodeling, 8/14/2024 - 10/30/2024
The existing washroom is being upgraded to be ADA compliant with some additional warehouse modifications.
Bldg. C, 2nd Floor Temperature Fluctuations, 9/30/2024 - 10/15/2024
Contractors are on campus to investigate HVAC issues in Building C, 2nd floor, from Monday, Sept. 30 through Tuesday, Oct. 15. There will be temperature fluctuations during this time.
Bldg. D, D110 Podcast Studio, 7/8/2024 - 10/30/2024
The classroom is being reconfigured to accomodate a sound booth. Room is available for classes however is will be offline Sept. 26-Sept. 29.
Bldg. H, H149 Storage Room Modifications, 6/15/2024 - 9/30/2024
Bldg. H, H190 Welding Lab, 7/1/2024 - 12/30/2024
Replacement of the smoke extractors and new LED lighting at the welding booths.This will have no impact to classes.
Bldg. LCC, Parking Lot Lights Upgrades, 5/28/2024 - 6/30/2025
Bldg. LCC, New Elevator, 11/2024 - 7/2025
There will be an elevator installed in the northwest corner of LCC. Work will begin late November or early December.
Bldg. M, Dance Floor Replacement, 11/25/2024 - 1/10/2025
Bldg. M, CO2 Tank Replacement/Relocation, 9/2024
Bldg. P, P105, 106 and 107 Audio Visual Lab Construction, 6/10/2024 - 11/29/2024
Installing new audio lab and classroom for recording studio.
Bldg. Y, Liebert Replacement Y211, 9/16/2024 - 10/4/2024
Contractor will be onsite on Thursday, September 26 between the hours of 6:00am and 4:00pm with a crane to lift mechanical equipment on to the roof of Bldg. Y for the Y211 Data Center Liebert Replacement project. See Map
Bldg. X, X110 Massage Therapy Remodel, 6/10/2024 - 9/30/2024
The area will be remodeled to update locker room/s, washroom and massage rooms.
Bldg. Z, Temporary Chillers, 5/1/2024 - 5/1/2025
Bldgs. XYZ, HVAC Automatic System Upgrades, 11/1/2024 - 6/30/2025
HVAC systems are being upgraded throughout all of the buildings to improve heating and cooling control.
Roselle Road Entrance, 10/21/2024
New landscape installation is scheduled for Monday October 21st at the Roselle road entrance.
Bldg. A Main Entrance, 9/9/2024 - 12/2/2024
In order to prepare for construction of the Canning Center, we are relocating the main ComEd line. The contractor is planning to start construction the week of Sept. 9. The affected area will be fenced (see attached site plan) and there will be no access from the North side to the circle driveway. Access from North to South will be blocked off. Students, Faculty and Staff can walk through or around Building Ato get to Building M. See map.
Sidewalk and Parking Lot Repairs - Campus Wide, 5/28/2024 - 9/30/2024
Contractors will be on campus to remove and replace deteriorated sidewalk sections throughout campus. All buildings will remain open and accessible during this time.There will also be contractors onsite performing our annual paving, sealcoating and striping maintenance. See Map.
Exterior Stair and Retaining Wall Maintenance - Campus Wide, 6/1/2024 - 9/30/2024
Maintenance and replacement of exterior stairs and retaining walls that were damaged.See Map
Steam Shut Down, 11/26/24 - 11/27/2024
In order to perform repairs, there will be a steam shut down starting at 10:00am on Tuesday, November 26 to be completed by Wednesday, November 27 at 9:00pm. There will be no heat or hot water to the entire campus during this time.