Harper College

Campus Construction

Buildings

Bldg. B to M Steam Piping, 5/24/2024 - 8/30/2024

Contractors will be repairing the steam piping from Bldg. B to Bldg. M.  This will affect multiple areas - Bldg. S, the elevated track in Bldg. M will be closed and the east side of the gym will be closed and only open for select events.

Bldg. E Film Screening Classroom Lab Project, 9/18/2023 - 9/30/2024

The northwest corner of Building E will be under construction until fall 2024 for the construction of the new Film Screening Classroom Lab. The entryway by the northwest corner of the building will be closed off until construction is complete.

Bldg. E Lobby and Restrooms Renovation, 5/20/2024 - 8/09/2024

The restrooms and the lobby of Bldg. E will be closed during this time period for renovation. The closest restrooms will be the west end of Building D.

Bldg. G Parking Garage Maintenance, 7/15/2024 - 8/31/2024

Contractors will be onsite to perform repairs and maintenance on the parking garage.

Bldg. H, H149 Storage Room Modifications, 6/15/2024 - 8/31/2024

Bldg. H, H190 Welding Lab, 7/1/2024 - 9/30/2024

Replacement of the smoke extractors and new LED lighting at the welding booths.

Bldg. H, H193 Classroom Modifications, 6/15/2024 - 8/31/2024

Bldg. LCC, Parking Lot Lights Upgrades, 5/28/2024 - 8/31/2024

Bldg. LCC, New Elevator, 12/2024 - 8/2025

There will be an elevator installed in the northwest corner of LCC.  We will provide additional updates as we get closer to a start date.

Bldg. M, Pool Maintenance, 8/5/2024 - 9/2/2024

The pool will be closed during this time for annual maintenance.

Bldg. P, P105, 106 and 107 Audio Visual Lab Construction, 6/10/2024 - 10/31/2024

Installing new audio lab and classroom for recording studio.

Bldg. P, Door modification, 5/28/2024 - 6/28/2024

Doors will be modified with glass lites.

Bldg. R Performing Arts Center Roofing Replacement Project, 5/17/2024 - 6/30/2024

Contractors will be on campus for several weeks to replace roofing on the Performing Arts Center.  On Friday, May 17, 2024, starting at 7:00am, there will be cranes delivering materials to the roof. See map.

Bldg. V Paving Project, 6/1/2024 - 8/16/2024

The area south of Bldg. V and northwest of the gym will be under construction.  Access along the west side of the gym will be restricted at times. See Map

Bldg. X, X250 Health Careers Office Remodel, 5/31/2024 - 7/5/2024

The reception area will undergo a refresh with new paint, carpet and furniture layout. Staff will temporarily reside in X246. 

There will be a dumpster in lot 4a directly in front of the entrance to Bldg. X from 5/31/24 to 6/7/2024.

Bldg. X, X110 Massage Therapy Remodel, 6/10/2024 - 9/30/2024

The area will be remodeled to update locker room/s, washroom and massage rooms. 

Bldg. X, Exterior Door Replacement, 6/24/2024 - 6/28/2024

Removing and replacing exterior double doors at the north entrance. 

Bldg. Z, Temporary Chillers, 5/1/2024 - 5/1/2025

Bldg. Z, Temperature Mixing Valves, 6/24/2024 - 8/31/2024

Replacing the thermostatic mixing valves for select eyewash stations throughtout the building.

All Campus

Bldg. A Main Entrance, 9/9/2024 - 12/2/2024

In order to prepare for construction of the Canning Center, we are relocating the main ComEd line.  The contractor is planning to start construction the week of Sept. 9.  The affected area will be fenced (see attached site plan) and there will be no access from the North side to the circle driveway. See map.

Sidewalk and Parking Lot Repairs - Campus Wide,  5/28/2024 - 8/31/2024

Contractors will be on campus to remove and replace deteriorated sidewalk sections throughout campus.  All buildings will remain open and accessible during this time.There will also be contractors onsite performing our annual paving, sealcoating and striping maintenance.  See Map.

Exterior Stair and Retaining Wall Maintenance - Campus Wide,  6/1/2024 - 8/31/2024

Maintenance and replacement of exterior stairs and retaining walls that were damaged. See Map

 

Last Updated: 6/27/24